WATER RESOURCES DEPARTMENT
GOVERNMENT OF NAGALAND

Status of minor projects taken up under AIBP/PMKSY-Har Khet Ko Pani:

Implementing agency: Water Resources Department

Sl.noName of ProjectYearCCA (Ha)Estimated cost (lakh)Status
1.468 Nos of Minor Irrigation (MI)Project1999-00 1455.920completed
2.74 Nos of Minor Irrigation (MI) Project2001-02 1539.900completed
3.1 Nos of Minor Irrigation (MI)Project2002-03 42.390completed
4.135 Nos of Minor Irrigation (MI)Project2003-04 1890.110completed
5.45 Nos of Minor Irrigation (MI)Project2005-06 423.480completed
6.173 Nos of Minor Irrigation (MI)Project2006-07 5054.870completed
7.70 Nos of Minor Irrigation (MI)Project2007-08 3597.190completed
8.166  Nos of Minor Irrigation (MI)Project2008-09 9155.510completed
9.177  Nos of Minor Irrigation (MI)Project2010-11 10799.605completed
1096  Nos of Minor Irrigation (MI)Project2011-12 5050.687completed
11120 Nos of Minor Irrigation (MI)Project2012-13 9122.355completed
12155 Nos of Minor Irrigation (MI)Project2013-14 11202.145completed
13159  Nos of Minor Irrigation (MI)Project2014-15 10960.347completed
14270  Nos of Minor Irrigation (MI)Project2016-17 20685.210ongoing
15213 Nos of Minor Irrigation project2017-18 13320.94ongoing
Total:   
Skip to content