Status of NHP Funded Projects

Implementing Agency: Water Resources Department, Nagaland

SL. No Year Location Name of the Project Approved Cost ₹ (In Lakh) Physical Progress Financial Progress
1 2019-2020 Kohima Construction of SDC at Kohima 119.76 Completed 100%
2 2019-2021 Dimapur Construction of HPCC at Dimapur 248.34 Completed 100%
3 2020-2021 Dimapur Purchase of Pygmy Type Currentmeter 1.98 Completed 100%
4 2020-2024 Kohima, Dimapur, Mokokchung, Tuensang, Mon, Kiphire, Phek, Peren, Zunheboto, Wokha, Longleng Supply, Installation, Testing, Commissioning and Maintenance of Real Time Data Acquisition System (RTDAS) for Nagaland 735.79 Ongoing 60%
5 2021-2022 Dimapur Supply, Installation, Testing, Commissioning and Maintenance of ADCP 35.85 Completed 100%
6 2021-2022 Dimapur, Kohima and Mokokchung Construction of Piezometers 17.44 Completed 100%
7 2021-2022 Dimapur Furnishing of Water Quality Lab 26.89 Completed 100%
8 2021-2024 Dimapur Development of Flood Forecasting Model in Dhansiri River 145.00 Ongoing 86.27%
9 2022-2024 Dimapur Alleviating Waterlogging Problem in Critical Areas of Dimapur 68.00 Completed 100%
10 2022-2024 Kohima, Dimapur Benchmarking of Minor Irrigation Projects Implemented in the State 30.00 Completed 100%
11 2022-2023 Dimapur Purchase of Current Meter with Fish Sounding 11.73 Completed 100%
Skip to content